Tag Archives: Permanent Way Gang

172/173- Chasewater Railway Museum Bits and Pieces

172 – Chasewater Railway Museum Bits & Pieces

From Chasewater News Autumn 1994 – Part 1

Permanent Way News

The second and final batch of track has now arrived from Four Ashes and is being put to good use by the Permanent Way Gang.  The works train has had to spend every Sunday ‘out of section’ at the end of the causeway just to make enough room for passenger trains, as with the amount of rolling stock now on site there is insufficient siding space at Brownhills West.  The track gang have put this situation to good use, and at the present rate of progress track will be in front of the platform at Norton Lakeside well before the end of this year.

In order to quantify the progress already made, and to assist with the planning of the future extension of the line, David Bathurst has produced the chart below showing distances between various points on the railway.

All distances were measured by pushing a pedometer along the head of the rail, and sleeper ends were marked with yellow paint at 100 metre intervals.  The ‘Zero Point’ was chosen as the gate post at the end of the loco shed yard, as after the motorway is built it is likely to be the closest surviving landmark to Brownhills West station.  When the time comes, new measurements can be made into the replacement station from the same spot.

The chart shows that we are currently running passenger trains over a distance of about a mile to the present running line limit almost half-way across the causeway.  When we ultimately reach Anglesey Wharf the total distance (estimated over the final section) will be around 2¾ miles, assuming that nothing is lost or added by the repositioning of Brownhills West Station (nice dream, but that’s all!).

173 – Chasewater Railway Museum Bits & Pieces

From Chasewater News Autumn 1994 – Part 2

Locomotive News

No.4 Asbestos – This engine has run exceptionally well considering the dubious start to the season.  Since then a total of twenty-two boiler tubes have been renewed and seem to have cured the problem of leakage at the firebox end.  Another 124 new tubes have now been acquired and are stacked in the shed ready to complete the re-tubing at the end of the running season.  Slight weepage of a few stays and part of the foundation ring will also have to be corrected.

The latest batch of Russian coal, although somewhat smoky, is giving excellent results without the problem of clinkering inherent in the last lot.  This is just as well, as with trains running every Sunday in this summer’s hot weather the last thing anyone wants to do is rake the fire through after every other trip.

Asbestos with a three-coach test train stands on the causeway ready to return to Brownhills West

No.5 Sentinel – Progress on this loco remains slow, although the boiler is now ready for its hydraulic test.  All of the boiler fittings have been refurbished and will be hydrauliced along with the boiler.  The injector has been moved to the fireman’s side of the cab and that and the Weir pump are being re-piped in such a way  that they can be drained easily in winter to prevent frost damage.

S100 – Work has continued with the manufacture of new mountings for the brake hangers to replace the original items which were somewhat bodged and worn out.

Fowler diesel hydraulic No.422015 – Replacement injectors have been acquired and fitted to the engine of this loco with the result that its performance has been transformed.  A few other minor problems have occurred, but it has remained in regular use for shunting and works trains.

Ruston diesel electric DL7 – One of the starting air valves of this loco has had to be renewed due to a damaged seat in the original.  A fuel leak from one of the injector pipes has also been rectified.  The loco is serviceable but has remained out of use mainly due to passenger trains being steam hauled throughout July and August.

Fowler diesel mechanical No.410013 – Following arrival from Redditch this loco has had its engine de-seized, the injectors have received attention and the engine has been run.  Faults have been found with the injection pump and governor and these have now been removed for attention.  Following completion of the air system overhaul the loco should be able to enter traffic.The new Fowler stands in the platform shortly after its arrival from Redditch

L&Y No1 (Motorail No.1947) – All of the axleboxes and springs have now been stripped and rebuilt and a new bearing is being made to replace one which was stolen recently.  Once the sandboxes and inside of the body castings have been stripped and primed the loco will be ready for craning from its present position in front of the museum coach so that final erection can begin.

No.21 diesel – This loco is making steady progress, the engine is now complete but still awaiting cylinder head gaskets.  It is hoped that it may be running for the Diesel Gala which is a new event to be held for the first time in September.

Lion – Following its removal to Foxfield last Autumn this loco entered service at Easter, running initially double-headed with ‘Harwarden’ The vacuum brake hoses were apparently awkward to couple as ours at Chasewater are the opposite side to ‘normal’ to suit our DMU stock.

Smith Rodley crane – This again remained out of use awaiting a potential purchaser.  So far a couple of enquiries have been received but no offers have been forthcoming.

From the Board Room

The Board has been actively involved in a number of new initiatives, while various on-going matters have been subjected to scrutiny and, where necessary, review.  The following will be of general interest to the membership.

1.    Personal circumstances have brought about the resignation from the Board of Les Emery.  However, Les has indicated a willingness to continue with his other roles on the railway.

2.    The Board has agreed to the co-option of Company Secretary Andy Clegg to the Board.

3.    The trading name of the company has been changed to the “Chasewater Railway”.  Previous official and unofficial trading (‘Chasewater Steam Railway’, ‘Chasewater Light Railway’, etc.) are no longer considered suitable and are felt to give a misleading impression of the nature of our current and future operations.

4.    In an attempt to encourage family travel during this period of continual financial restraint, the price of the Family Rover has been reduced, until further notice, from £5.80 to £4.95.

5.    During the course of the nest few months, the Board is to produce a new business plan for the purpose of clearly defining objectives and priorities, and how they might be best achieved within the resources (including financial and manpower) expected to become available.  Associated with this proposal is the revival of the concept of departmental heads, holding pre-determined budgets, to give focus to the completion of the many and varied tasks necessary for the railway to both exist and develop.

6.    The Board has responded to a plea from Rallies Organiser Dave Whittle by delegating various aspects and responsibilities to specified individuals.  Thanks largely to the efforts of Dave, the Chasewater Rallies are rapidly gaining in reputation, with Paul Richards taking up much of the strain as Administrative Officer.

7.    On other fronts:

·        Negotiations are proceeding with HM Railway Inspectorate in relation to the extension into, and construction of, Norton Lakeside Station.

·        The railway was represented at a meeting of Chasewater user groups hosted by Lichfield DC, and arranged on a largely social basis for the various groups to meet the Members and relevant Officers of the District Council.

·        Lichfield District Council has generously offered grant aid to the railway in the sum of £1,000 by way of a contribution towards forthcoming expenditure.  This generous act by the District Council signals a solid measure of support for the railway by its new ‘landlord’.

·        Accommodation at Brownhills West has become a problem in consequence of stock acquisition, (4 DMU coaches plus one tanker wagon).  However, this should be relieved by the imminent removal of one (at least) of the Wickhams, and the Board is still anxious to dispose of the crane (preferably to a good home on another railway) as a matter of priority.

·        The transfer of records from Adrian Hall should enable Paul Richards to take up his responsibilities as Membership Officer with early effect.

·        The Board has agreed strategy towards bidding for the trackwork at Bromford Sidings, and has noted that the remaining trackwork at Four Ashes is due to transfer to Chasewater in August.

David Bathurst – Chairman.

139 – 137 Chasewater Railway Museum Bits and Pieces

139 – Chasewater Railway Museum Bits & Pieces

From Chasewater News Autumn 1991 – Part 2

How it was, how it is and the 1st Burntwood Scouts

 Initially we started the track attack around Jan/Feb 1990, but an accumulation of other, more pressing jobs needed our attention.  As a result, it was decided to leave the planned track extension until a later date, which was more or less twelve months later.

How it was.

After laying 50 odd concrete sleepers between two of us, just Pete and I, we came to the conclusion that the rails were out of true, that is, they were not in uniform lengths.

We concluded that it would take more than two of us to correct this problem so we decided to leave it until later in the year, and, as stated earlier, other jobs required more urgent attention.

Meanwhile, it had been decided that the various departments of our railway required better leadership, and as a result, Les Emery became our Permanent Way foreman.

Firstly, I suppose he felt like any other p-way ganger would, that trundling down 1,000 or so yards of track to nowhere specific causes enthusiasm to wane a little.  Secondly, he seems the kind of bloke who has the uncanny knack of proving the need for his actions, and if a job should crop up, would rather do it first than answer for it later.  Now the p-way gang get even the most tedious jobs done, whether it is weedkilling, tightening fishplate bolts, or even cutting back the grass banks or trees.  Using a shovel and sweat (unless some kind soul out there has got an old JCB to lend us?) quite a lot has already been achieved.How it is.

Things are coming on nicely thank you.  Since starting the ‘track attack’ in February, Les came up with a brilliant idea for moving 60 foot lengths of rail with only about three blokes, by the use of three small rollers onto which the rail can be jacked and then pushed along.

Our gallant leader believes that we could be at the bottom of the causeway bank by the end of October, others reckon spring 1993, and that id laying the track, ballasting and having it passed by the Railway Inspectorate.

Ur long term ambition is to relay the track as far as Anglesey Wharf, which is close to the bad canal bridge in Wharf Lane.  Mind you, that’s a long way off yet, but the way things are going, could be in the next ten years or so.

Our main concern will shortly be the causeway bank which has got to be braced and backfilled as the water has eroded the banks on either side.  The ‘spiky bridge’ also needs repair; I wonder if it will still be called the ‘spiky bridge’ once it is repaired?  We are fortunate to have no underbridges on this railway, just the two overbridges.

It is hoped to use the existing platform built years ago by the Manpower Services Scheme on the other side of the causeway.  This would be the end of our extended run until further rail and sleepers could be obtained.

Our track attacks take place once a month, with minor maintenance jobs done in between.  With our line getting ever longer, weedkilling by watering can is tending to become an all day job.  A big tank with a spray pipe at one end could be a solution to the problem.After the toe rags smashed the Willow Vale bridge handrails off completely, Dave, Keith and Paul fabricated new handrails using old bullhead rail so that should, I pray, be that job done.

I should mention the great help we had from the Burntwood Scouts during the May track attack – it was much appreciated – cheers.

Arthur Edwards

The 1st Burntwood Scouts and the May Track Bash

1st Burntwood scouts were one of the largest scout groups in the Lichfield District.  They had just under 200 members ranging from 7 year old Beavers through to 20 year old young men and women in the Venture section.

Whilst many of the activities have changed over the years, to meet the challenges of today’s society, one activity which is still central to scouting is that of helping others.  This can take many forms, but one in particular is that of becoming involved in the local environment.

When Dave Whittle mentioned that the Chasewater Light Railway hold regular sessions to clear and extend the running line, the Jupiter Troop of scouts thought that this would not only be a worthwhile environmental project to become involved in, but might also be good fun.

As it turned out the boys who came along all thoroughly enjoyed themselves, put a bit of work in as well, and went home both tired and wanting to return.  Now that we have made the contact, we will be bringing parties of scouts along to help out in any way that we can.

1st Burntwood Scouts.The scouts pose with the CLR track gang in front of the works train at the end of the May ‘track bash’.

137 – Chasewater Railway Museum Bits & Pieces

From Chasewater News April 1991 – Part 5

More Sid Browne Memories – Pete Aldridge

Flat Tyres

Whilst industriously playing cards one morning in the1960s at Bescot, Sid was summoned to the foreman’s office.

‘Sid’ said the foreman, ‘There’s a special test train waiting at Wolverhampton.  They haven’t got a guard, so I’m sending you along.’Gateway to the high level railway station

This building is described thus on a blue plaque erected by the Wolverhampton Civic Society:
“The Queen’s Building. Gateway to the High Level Railway station. Erected 1849. Edward Banks, Architect.”
It is located a short walk away from the mainline station. The bus station is located beside it.   © Copyright Ruth Sharville and licensed for reuse under this Creative Commons Licence.

Sure enough a taxi arrived and took Sid to Wolverhampton High Level.  The special train consisted of four brand new electric locomotives, two at each end of a test coach.  It all looked very impressive.  Alas, no-one had a key to open the doors on the coach, so Sid, a petite sixteen and a half stone, had to force his way in through the corridor connection.  The key was hanging up in a corner of the coach.

Eventually everyone got on board.  The driver of the electric loco was told ‘You’ve got a clear path through to Stafford.  Go as fast as you can from here and don’t stop no matter what we do with the brakes until we get to Stafford.

‘Hello!’ thought Sid ‘This should be fun.’

The train started off and rapidly picked up speed.  ‘Just a minute! called one of the inspectors, ‘The handbrake’s still on the coach!’

‘So take it off then’ chimed another inspector.

‘Could be tricky,’ said Sid ‘It’s external; there’s no way of getting at it from in here.’

The inspector applied the vacuum brake, but to no avail, the driver was carrying out hid instructions to the letter.

What a sight it must have been, four gleaming electric locos, pantographs sparking and flashing, with the tyres of the test vehicle flashing and sparking as well.  As it turned out, the driver did not get the clear run he had been promised, and the train stopped near Penkridge.  The inspectors hurriedly released the handbrake and climbed back onto the train.  The signals changed and the driver set off once more.

‘THUMP THUMP THUMP’ went the coach wheels, which had huge flats on their tyres.  The train accelerated up to Ninety miles an hour.  ‘THUBITY THUBITY THUBITY’ the coach shook and vibrated.   Things fell of shelves and out of cupboards.  This was unbearable.

At long last the train arrived at Stafford.  ‘Everything OK?’ asked the driver as he climbed down from his electric.  The test crew, plus Sid, were ashen faced and feeling far from well.

‘No, not really,’ replied the inspector, and was promptly sick!The first ‘Peak’ Diesel leaving Stafford on an Up express View NW, towards Crewe etc. on the WCML. By 1960 many WCML expresses had been handed over to Diesel haulage: here No. D1 ‘Scafell Pike’, the first BR/Sulzer ‘Peak’ 2,300hp Type 4 1-Co-Co-1 (later Class 44 No. 44.001), pulls the 08.30 Carlisle – Euston out of Stafford station.  © Copyright Ben Brooksbank and licensed for reuse under this Creative Commons Licence.